Camp Crone Rd Project

Information on Camp Crone Rd Project - this is a 5 phase project:

  • Phase 1: West Lake Rd to House #463 includes the removal and replacement of asphalt and sub-base. Installation of two catch basins to catch storm run-off from roadway. Scheduled to be completed September/October 2017
  • Phase 2: House #463 to House #467 includes removal and replacement of asphalt and sub-base. Scheduled to be completed in September/October 2017
  • Phase 3: House #467 to House #471 includes removal and replacement of asphalt and sub-base. Scheduled to be completed in September/October 2017
  • Phase 4: House #471 to Swim Area Gate includes minor sub-base rehabilitation and re-surfacing. Scheduled to be completed in Spring 2018
  • Phase 5: Swim Area Gate to end of road near House #477 includes minor sub-base rehabilitation as required and resurfacing. Scheduled to be completed in Spring 2018

We are using a $100,000 grant to have Phase 1-3 completed by a contractor (Adhan Piping) over the coming weeks. I will communicate further with the property owners as a construction schedule is completed. We just received the final contracts and are scheduling a pre-construction meeting soon. 

For Phases 4 & 5 we will be utilizing town resources (equipment, labor, and funds) to complete prior to the summer season next year.

News & Events 1.22.13

What do you do with the kid(s) when you don't have a spotter and no gas in the boat?

Read More Read ALL

Local News 1.20.18

35 Central NY students advance to oral round of spelling bee

The oral spelling bee will be held live on WCNY-TV at 2 p.m. on Feb. 10....

Read More